It’s been a while since we last talked about the progress of the construction sites of our first portfolio, Coversol 1. For simplified handling of the 44 projects, we have divided the portfolio into three groups (A, B, C), with roughly equal capacity.
Here is a breakdown of the latest developments:
Group A: Almost all projects have finished construction. Ten of those projects are already grid connected and producing electricity.
Group B: Half of the projects in this group have completed construction, with the first two expected to be grid connected before the end of the year.
Group C: Construction kick-off for this group is scheduled for the end of January.
With this the halfway point for the construction has been reached, marking a significant milestone for the portfolio!